Amount recoverable
A more obvious distinction between civil and common law legal systems can be seen in relation to claims for liquidated damages, where the parties have fixed an agreed rate of damages that must be paid by a party if that party fails to meet a contractual obligation - usually to complete by a contractually required date or within a contractually required period.
The position in many common law jurisdictions is that, to be enforceable, the liquidated damages must be a genuine commercial pre-estimate of likely loss and must not amount to a penalty. In most civil law jurisdictions, however, the focus is different. Here, a balance is found by codified principles - for example, in the Middle East, where contractually agreed damages can be reduced if the party levying the damages did not suffer damage to the full amount claimed.
In other civil law jurisdictions, the scope for damages is wider because civil law systems often entail an additional obligation to those expressly set out in the contract - the obligation to perform contracts in good faith. Common law systems have also recognised the principle of ‘good faith’, albeit to varying degrees of importance.
Approaches to claims for damages
Claims for damages typically involve the identification of a breach of contract. In both common law and civil law jurisdictions, the essential ingredients of an actionable claim are:
- breach;
- loss; and
- causal link between the breach and the loss.
Both types of legal system have requirements regarding remoteness or ‘foreseeability’ of the damages suffered - that is, the damages must not have been too remote; must have been in the contemplation of the parties; or must be a natural consequence of the breach.
Although some civil law jurisdictions do not prescribe the requirement to mitigate the loss suffered as a result of a breach of contract, others specifically do.
Approaches to global claims
A global claim is one in which the contractor expresses its entitlement to a sum of money based on a series of events without showing the causal link between each and every individual event identified and the loss suffered as a result.
Global claims are widely resisted in common law jurisdictions, unless a unique set of circumstances exist. These were most recently set out in the English case of Walter Lilley v Mackay.
In practice, global claims are often less successful because by their nature the claiming party does not undertake the usually rigorous process of linking the amount of damages claimed satisfactorily to the delays or other issues complained of - thus, on the face of it at least, not meeting the burden of proof requirement in the relevant legal system. However, they are not impossible to pursue, provided the claiming party does a suitably rigorous job of describing and quantifying the claim.
The term ‘global claim’ is generally unfamiliar to judges tasked with determining liability in civil law jurisdictions, with some minor exceptions. However, if followed, the principles expressed in the Walter Lilley case would be equally persuasive in civil law jurisdictions as they have been shown to be in common law systems.