OUT-LAW ANALYSIS

Queensland's Construction Productivity Code: what contractors need to do now

Builder with concrete blocks stock_Digital - SEOSocialEditorial image

The Queensland Construction Productivity Code 2026 took immediate effect upon its implementation on 17 November 2026. lovro77/iStock.


Contractors working on major Queensland Government construction projects, including projects forming part of the Brisbane 2032 Olympic and Paralympic infrastructure programme, should urgently review their industrial relations, safety and compliance arrangements to ensure they adhere to the new Queensland Construction Productivity Code 2026 (Code).

Non-compliance with the Code will not raise merely project-level compliance issues. It may put a contractor's ability to secure future Queensland Government work at risk.

Contractors in-scope of the Code should move quickly to:

  • audit enterprise agreements and existing workplace arrangements for provisions or practices that may be inconsistent with the Code;
  • review and update workplace relations management plans (WRMPs);
  • establish an effective internal escalation process capable of meeting the Code's 24-hour reporting requirements;
  • clarify who has authority to make decisions when industrial relations or work health and safety (WHS) issues arise; and
  • review subcontracting arrangements and contractual terms to ensure Code compliance is appropriately addressed throughout the supply chain.

The Code was implemented by the Queensland Government on 17 November following recommendations made in the interim report of the Commission of Inquiry into the Construction, Forestry and Maritime Employees Union (CFMEU). The aim of the Code is to improve productivity, safety and cost efficiency on government-funded projects.

For contractors, the significance of the Code extends beyond those broader policy objectives. It introduces substantive compliance obligations affecting industrial arrangements, site practices, subcontracting, WHS, reporting and the management of workplace disputes. In some cases, contractors may have only 24 hours to respond to and report an issue.

Scope of the new Code

The Code, which took immediate effect, applies to contractors on publicly funded construction projects valued at AUD$150 million (US$100m) or more. Contractors covered by the Code must comply with specified workplace, safety and industrial relations standards.

Although the Code is not intended to operate retrospectively, approval has been granted for its application to the Brisbane 2032 Olympic venue projects. This is likely because of the significant consequences of those projects being not being completed on time, and that those projects have or will attract a strong union presence.

That is particularly significant for contractors already engaged on those projects. Those contractors now need to consider whether workplace practices, enterprise agreements, WRMPs and existing contractual arrangements are capable of operating consistently with the new regime.

Contractors must now take all reasonable steps to ensure that their workplace practices and contractual arrangements support compliance of the Code, which will be enforced through the Department of State Development, Infrastructure and Planning (DSDIP). Accordingly, compliance cannot be treated simply as an issue to be addressed when tendering for new work. For contractors on affected projects, it is now an ongoing project-management and workplace-relations issue.

Enterprise agreements and workplace practices are squarely in focus

Where contractors are covered by an enterprise agreement, which most are, they must disclose any provisions that do not comply with the Code and explain how they will be able to demonstrate the impact on costs, productivity and timely delivery. 

The Code requires that the industrial instrument not:

  • prescribe or limit the number of employees or workers to be engaged on a particular site;
  • set out one-in-all-in arrangements, such as in relation to overtime;
  • include last-on, first-off redundancy selections;
  • contain a provision that restricts an employer’s short or long-term labour requirements, nor provisions that stipulate the terms and conditions for the labour of any person not a party to the industrial instrument; or
  • include relaxation of the right of entry provisions.

Therefore, contractors should not assume that an existing, legally operative enterprise agreement can simply continue to be administered in the same way on a Code-covered project. The relevant agreement, together with the workplace practices operating alongside it, should be reviewed against the Code.

For contractors already working on Brisbane 2032 Olympic projects that have an existing enterprise agreement, that review is particularly important because relevant enterprise agreements and workplace arrangements may have been negotiated or implemented before the Code applied to the project.

The Code also prohibits requirements to disclose union membership or engage union-nominated workers or non-working shop stewards. Contractors will not be required to allow union flags, “no ticket, no start” signs, or “show card” days.

These changes are aimed at ensuring industrial relations issues and disputes do not decrease productivity or increase project costs. The Commission of Inquiry found that the Best Practice Industry Conditions, a former government procurement policy, caused project cost overruns of about 20%.

New compliance obligations for contractors

One of the most significant practical features of the Code is the speed with which contractors may need to act.

Principal contractors must, within 24 hours of becoming aware of threatened, possible, likely or actual unlawful industrial conduct or a breach of the Code, report relevant industrial relations or WHS grievances or disputes to DSDIP.

That makes internal escalation critical. A contractor cannot reliably meet a 24-hour external reporting obligation if a significant site-level issue takes longer than that to reach the people responsible for deciding whether a report is required.

Accordingly, contractors should have a clear protocol setting out:

  • what types of conduct or disputes must be escalated;
  • who on site is responsible for raising the issue;
  • who receives that escalation within the business;
  • who determines whether a notification to DSDIP is required;
  • who is authorised to obtain urgent legal or industrial relations advice; and
  • how the relevant facts, decisions and notifications will be documented.

Site managers, project directors and other personnel responsible for industrial relations and WHS should also understand that an issue does not necessarily need to have matured into an actual contravention before the reporting requirement becomes relevant.

The breadth of the obligation means that waiting for an industrial issue or WHS dispute to resolve itself before escalating it internally could expose a contractor to unnecessary compliance risk.

Principal contractors also face the most significant burden under the Code given the obligations placed on them. For example, they are required to prepare and comply with a WRMP, which must address 18 areas from labour sourcing, productivity, safety and workplace relations. 

Under the Code, they also:

  • have overall responsibility for WHS on projects and must take all reasonable steps to ensure their suppliers and workers comply;
  • within 24 hours of becoming aware of any threatened, possible, likely or actual unlawful industrial conduct or breach of the Code, report to DSDIP any industrial relations or WHS grievances or disputes; and
  • use all reasonable efforts to pursue legal remedies to protect their rights and obligations under the Code.

The WRMP should therefore operate as more than a tender or compliance document. Contractors should test whether what is written in the plan reflects what actually happens on site, including how industrial disputes are escalated, how right-of-entry issues are dealt with, how subcontractors are managed and how potential Code breaches are identified and reported.

While subcontractors are only subject to the Code requirements that are relevant to the work or services they perform, they must, so far as is reasonably practicable, comply with the Code and all legal requirements within their control.  In particular, subcontractors must:

  • provide a warranty that they will comply with the Code;
  • allow DSDIP to inspect relevant work, records and documents, and interview people where needed to verify compliance;
  • not engage sham contracting, arrangements designed to avoid legal duties or strike-pay obligations, improper right-of-entry arrangements, or practices that undermine freedom of association;
  • meet all applicable WHS obligations and maintain appropriate safety, risk-management, training, incident-reporting, rehabilitation and record-keeping practices; and
  • report suspected breaches to DSDIP within 24 hours.

For principal contractors, this means Code compliance is an ongoing condition of participation in Queensland Government construction work. Contractors must cooperate with compliance monitoring and demonstrate adherence throughout the life of a project. Existing subcontracting templates, warranties, reporting provisions and escalation mechanisms should be reviewed to ensure they give the principal contractor both the information and contractual rights needed to manage its own obligations under the Code.

Most significantly in practical terms, the consequences of non-compliance do not necessarily end with the project on which a breach occurs. A breach may put a contractor's eligibility to tender for and secure future Queensland Government work at risk.