On 30 September, following an extensive early contractor involvement (ECI) process, the Games Independent Infrastructure and Coordination Authority (GIICA) announced that the BESIX Watpac and John Holland joint venture had progressed to the final stage of the contractor selection process for Victoria Park Stadium.
The joint venture will now work with GIICA and the stadium's design team to finalise design and construction methodologies ahead of construction commencing in mid-2027. Early works at Victoria Park, being undertaken by Queensland-founded BMD, are already under way with more than 200,000 cubic metres of earth and rock, the equivalent of 80 Olympic swimming pools, moved in 100 days.
Separately, on 15 November, the Gather Brisbane consortium, comprising Plenary, Live Nation, Oak View Group and Webuild, was selected to deliver the Gabba Entertainment and Housing Precinct. The consortium will design, build, finance, maintain and operate a new 17,000-seat indoor arena adjacent to the Woolloongabba Cross River Rail station before the Games and deliver 4,000 residences on the former Gabba Stadium site following its decommissioning.
Construction of the arena is expected to begin in early 2027 and conclude in 2031. The project is being privately financed, with the Queensland government not contributing its share of capital funding until the venue opens. The consortium will also be responsible for maintenance and refurbishment obligations, while the state will retain ownership of the land.
On the Sunshine Coast and building on the award of design and pre-construction contracts for Stage 1 of The Wave Rail project between Beerwah and Caloundra in late May, on 18 November, SunLinQ, comprised of BMD, CPB, GS and UGL, was announced as being awarded the design and pre-construction contracts for Stage 2 between Caloundra and Birtinya. Like Stage 1, Stage 2 will be dual track with a tunnel also included at Little Mountain.
Escalation risks threaten budget certainty
GIICA is responsible for delivering 17 new and upgraded venues, including Victoria Park Stadium and the National Aquatic Centre. Venue infrastructure funding is capped at A$7.1 billion (approx. US$4.77 bn) with the Commonwealth contributing up to A$3.4bn. Any cost overruns are therefore likely to be borne by the Queensland government.
While the Queensland government has acknowledged that the Games operating budget established in 2021 no longer reflects current realities, it has remained firm that the venue infrastructure budget will not increase.
That position will be tested by conditions across global construction markets. Ongoing conflicts in Ukraine and the Middle East, supply chain instability, insurance pressures and higher energy costs continue to drive volatility in labour and material prices. Together, these factors may make it increasingly difficult to deliver Games infrastructure within existing budget allocations.
A February 2026 report by WT Advisory identified material costs as a key driver of escalating costs in Queensland's construction sector. The report forecast an annual escalation of between 5.8% and 10% throughout 2026 to 2028, coinciding with the period in which most major Games venue procurement and construction activity is expected to occur. It also highlighted growing energy and insurance costs as additional sources of pressure. The report suggests construction cost growth is likely to remain above long-term averages throughout the lead-up to 2032.
Similar conclusions were reached by Construction Skills Queensland in March 2026. The report estimated that total Games-related construction activity, including athlete villages and precinct developments, could reach A$11.2bn. It described Queensland's construction sector as being in a "super-cycle" driven by population growth, the energy transition and Games delivery, while also highlighting declining productivity and a statewide infrastructure pipeline valued at between A$53bn and A$75bn.
Infrastructure Partnerships Australia has further highlighted the scale of investment occurring across Queensland. Its report found that the state had allocated A$75.4bn in infrastructure expenditure over the four years to financial year 2029-30, an increase of more than A$4bn compared to the previous budget. Queensland ranked first nationally for infrastructure investment at a time when overall infrastructure spending elsewhere in Australia was moderating.
Together, these reports point to increasing competition for labour, specialist contractors and key materials as Games construction gathers pace.
Queensland's constrained housing market presents another challenge. As labour and resources are absorbed into Games-related infrastructure projects, fewer tier-one contractors may compete for private residential developments. This could place further upward pressure on housing construction costs while creating opportunities for less experienced contractors to fill the resulting gap. The workforce expansion needed to meet Olympic delivery deadlines may add further economic and political pressure during the peak construction period.
Procurement strategies will be critical
Recent developments surrounding Victoria Park Stadium demonstrate the growing importance of early contractor engagement.
ECI processes allow principals and contractors to identify and address escalation risks before contracts are finalised. Early involvement can help identify long-lead procurement items, test construction programs and develop pricing mechanisms that better reflect prevailing market conditions. Their success, however, will depend on whether those insights are translated into commercially sustainable contractual arrangements.
Traditionally, escalation risk has often been managed through fixed-price lump-sum contracts. Experience during the Covid-19 pandemic demonstrated the limits of such an approach. Transferring this risk down the contractual chain can increase the likelihood of contractor and subcontractor insolvency, ultimately threatening project delivery itself.
Contractors are now far more alert to escalation risk and are increasingly reluctant to assume it without appropriate compensation. Against a backdrop of mounting political scrutiny, a fixed delivery deadline and continuing market volatility, governments may face pressure to adopt more flexible procurement models.
Potential approaches include collaborative contracting arrangements, such as alliancing models with pain-share and gain-share mechanisms, which distribute risk more evenly across project participants and can better accommodate market uncertainty than traditional fixed-price contracts.
Dispute avoidance measures may also become increasingly important. Where escalation risks are not adequately addressed through the contract itself, contractors may seek to recover losses through formal dispute processes. Dispute avoidance and adjudication boards can reduce the risk of protracted disputes while preserving project momentum.
Another possibility is the strategic procurement of critical materials. Contractors involved in ECI processes may encourage project owners to secure key materials through bulk purchasing arrangements or central stockpiles to lock in pricing and improve supply certainty. Such approaches, however, introduce additional considerations, including storage, insurance, deterioration and design-change issues.
Where collaborative models are not adopted, greater reliance is likely to be placed on contractual escalation mechanisms.
Rise and fall clauses allow contract prices to adjust in response to changes in labour, fuel or material costs, providing protection against significant price movements while allowing principals to cap overall exposure.
Index-linked clauses provide a similar function by linking price adjustments to objective benchmarks such as the consumer price index, reducing the likelihood that either party bears the full consequences of changing market conditions.
Contractors should also remain alert to regulatory intervention. A recent example was the Fair Work Commission's road transport contractual chain order, introduced in April 2026 in response to rising fuel costs. Although the relevant fuel recovery obligations ceased in June 2026, the order demonstrated how regulatory action can alter carefully negotiated risk allocation frameworks and impose obligations on businesses further up the supply chain.
History suggests Olympic infrastructure projects rarely remain within their original budgets, and current market conditions increase that risk for Brisbane 2032. For GIICA, the challenge will be balancing budget discipline against the commercial realities facing contractors and suppliers. Procurement strategies that allocate escalation risk fairly and sustainably are likely to play a critical role in ensuring Games infrastructure is delivered on time and without significant disruption to the supply chain.
Co-written by Matthew Gowlett and Amber Shostak of Pinsent Masons.