It is not sufficient to base incentives for consultants or subcontractors solely on their own performance against their contract targets. For example, a consultant with his own target may be tempted to devote insufficient resources to the design stage, which may go on to lead to the alliance incurring additional costs in improving the design later in the project. Here, the consultant may beat his own target but, as a consequence, put the wider alliance into 'pain'.
Where a subcontractor causes loss, what remedies are available to the alliance members? As a target cost contract works on the basis that all costs are reimbursable, contractors will be reimbursed for their own additional costs and those of other supply chain members which arise because of the subcontractor's breach.
The tier one loss is a reduction in the gain it would have made or an increase in the pain as a result of exceeding the target. It is an unusual head of loss, and must be catered for in the subcontract terms.
The main contract often has a term that if the employer pays out as a result of subcontractor defaults, the main contractor is required to pursue any resulting losses. Often this is expressed as an indemnity and outside of any 'no claims' clause. For the main contractor, a potential safeguard is to ensure that the project board has the right to decide if proceedings are in the best interests of the project.
Nigel Blundell is a construction expert at Pinsent Masons, the law firm behind Out-Law.