Event
|
GCC 1999
|
MTRC
|
HKAA 2011
|
HKIA 2005
|
NEC3
|
|
Suspension (if ordered by employer / engineer / architect due to outbreak)
|
Time and money
(clauses 50(1)(b)(viii), 54(2)
|
Time only
(clauses 68.1(h), 72.1 and 72.2)
|
Time and money
(clauses 44.3(a)(xii), 49.1 and 55.1(xii))
|
Time and money
(clauses 23.3(c), 25.1(3)(j) and 27.1(2)(e))
|
Time and money
(clause 60.1(4))
|
|
Force majeure (if coronavirus outbreak is a "force majeure" event)
|
No force majeure clause therefore no time and no money
|
No force majeure clause therefore no time and no money
|
No force majeure clause therefore no time and no money
|
Time only
(clause 25.1.3(a))
|
Time and money:
not force majeure but an event neither party could prevent (clause 60.1(19)); clause often amended so only time not money
|
|
Change in law (if contractor needs to comply with any new law or regulation in relation to coronavirus)
|
No time and no money
|
No time and no money
|
No time and no money
|
No time and no money
|
Potentially time and money
if provided for in NEC Option X2 / additional condition
|
|
Instruction by the employer / engineer / architect to take “special work arrangements”
|
Potentially time and money
if amounts to suspension (see above), access restriction (clause 50(1)(b)(vi)), or variation (see below)
|
Potentially time and money
if amounts to suspension (see above), access restriction (clause 65), or variation (see below)
|
Potentially time and money
if amounts to suspension (see above), access restriction (clause 42), or variation (see below)
|
Potentially time and money
if amounts to suspension (see above), access restriction (clause 25.1.3(s)) or variation (see below)
|
Potentially time and money
if amounts to a suspension (see above), access restriction (clause 60.1(2)), variation (see below), or breach (clause 60.1(18))
|
|
Delay in delivery of materials (from China due to the coronavirus)
|
No time and no money.
Contractor is generally responsible for materials and delivery (clause 10) - if material is to be provided by employer then money only (clause 63(e))
|
No time and no money.
Contractor is generally responsible for materials and delivery (clauses 1.1.60 and 10.1(c))
|
No time and money with no such express provision.
|
No time and no money
Contractor is generally responsible for materials and delivery (clause 8.1.1) - if material is to be provided by the Employer then time and money (clauses 25.1(3)(r) and 27.1(2)(j))
|
Potentially time and money
See under force majeure above, also entitlement where supplies by employer or third parties (clauses 60.1(3), (4), (16) and (18)); but clauses often amended so only time for neutral events and delays by third parties
|
|
Variation (if coronavirus led to variation as defined in contract)
|
Time and money
(clauses 50(1)(b)(iv) and 63(b))
|
Time and money
(clauses 68.1(b) and 80)
|
Time and money
(clauses 44.3(a)(xiii) and 55.1(xv))
|
Time and money
(clauses 25.1(3)(h) and 27.1(2)(c))
|
Time and money
(clause 60.1(1))
|
|
Delay as a result of engineer / architect / employer's flexible working arrangements
|
Potentially money only (clause 63(a))
|
Potentially time and money (clauses 7.4, 9.7, 16.4 and 68)
|
Potentially time and money (clauses 7.5, 44.3(a)(i) and 55.1(i))
|
Potentially time and money (clauses 25.1(3)(l) and 27.1(2)(g))
|
Potentially time and money (clauses 60.1(3), (5), (18) and (19)); clauses often amended so only time for neutral events and delays by third parties
|
|
Any other special circumstance
|
Time only (clause 50(1)(b)(xi))
|
No similar blanket provisions - not within meaning of "excepted risk"
|
No similar blanket provisions - not within meaning of "excepted risk"
|
No similar blanket provisions - not within meaning of "excepted risk"
|
Potentially time and money:
see under force majeure above
|