A construction contract will generally set out the relationship between two or more parties, each party's obligations towards the other and what remedies are available if one party does not meet those obligations.

However, in the majority of circumstances the law creates other remedies that will be available to the parties regardless of what is provided in the contract.

In order to create certainty, the parties may wish to limit the scope of what each can claim for. They can do so by using a clause – often called an 'exemption clause' which limits each party's liability to that which is set out in the contract.

There are various ways of limiting liability in a contract. These include:

  • listing certain types of loss that a party will not be liable for,
  • stating that the contract contains the whole of the parties' agreement;
  • setting a limit on the amount of damages a party will be liable for;
  • excluding certain remedies that would otherwise be available to the party that is not in breach.

Incorporation and construction

An exclusion clause must be clearly shown to be incorporated into the contract using clear, unambiguous language. If there is any doubt or ambiguity in the clause, then the clause will be interpreted against the party relying on it – that is, the party seeking to limit its liability. This is known as the 'contra proferentem' principle.

A case in 2010 involving British Gas showed how carefully exemption clauses have to be drafted if they are to be effective. British Gas, trading as Centrica, hired consultancy firm Accenture to design, supply, install and maintain a new billing system. There were considerable errors and delays in the implementation of this system. In March 2006 the parties entered into an amended agreement to release an amended billing system, but by June of that year a considerable number of errors had emerged which resulted in increased numbers of customer accounts that were not billed properly and unhappy customers. In February 2007, Centrica notified Accenture about certain 'fundamental defects' in the billing system, but Accenture refused to take any steps to rectify those errors.

There was a clause in the companies' contract which said that liability for loss of profits and indirect loss were excluded, meaning that neither side would have to pay damages to cover those sort of costs.

Centrica wanted Accenture to pay for losses including the compensation offered to its customers and additional borrowing charges it had taken out and the High Court found that these losses were neither loss of profits nor were they indirect losses. Consequently the losses did not fall within the 'loss of profits' and 'indirect losses' exclusion. This was confirmed by the Court of Appeal. Accenture was therefore liable to pay those losses.

The court said that if Centrica was to be considered to have given up its rights to claim for the damages it did then the language in the contract would have to have specifically outlined these as excluded categories of damages.

The Unfair Contract Terms Act

The Unfair Contract Terms Act (UCTA) limits companies' ability to avoid liability in their contracts. UCTA is only concerned with exclusion clauses, and does not examine whether a contract is generally unfair. An 'exclusion clause' is not fully defined in UCTA, but can include any clause attempting to:

  • restrict or exclude liability;
  • make a liability, or the enforcement of a liability, subject to restrictive conditions;
  • restrict the rights and remedies of the wronged party; or
  • restrict rules of evidence or procedure.

Exclusion clauses that are subject to these provisions will either be void in all cases, or void where they fail a test of 'reasonableness'. UCTA does not apply to international supply contracts.

An exclusion clause can never exclude remedies for:

  • death or personal injury;
  • breach of statutory implied terms in consumer contracts.

Different provisions of UCTA apply depending on which type of exemption clause is used and on whether the other party is a consumer or another business. Many construction contracts are concluded between two business entities. In these cases, under English law a party's attempts to limit liability will usually be subject to a test of reasonableness – that is, they will be found by a court to be void if the court considers that they are unreasonable.

For example, a clause purporting to limit or exclude a party's liability for negligence – other than negligence which causes personal injury or death, which cannot be limited in any way – will only be effective if it is reasonable. A clause purporting to limit or exclude a party's liability for breach of contract will be subject to the reasonableness test if the other party is a consumer or if the other party is a business and the parties have contracted on one of the parties' written standard terms and conditions. If both parties are businesses and have not contracted on either's standard written terms and conditions then clauses limiting or excluding liability for breach of contract are not subject to the reasonableness test.

Entire agreement clauses

An entire agreement clause is a special type of exclusion clause. It states that the entirety of the agreement between the parties is set out in the contract and limits the liabilities of the parties to a contract to only what is covered under that contract.

An entire agreement clause cannot exclude fraud, such as fraudulent statements made during pre-contractual negotiations.

The elements that an entire agreement clause needs in order to be effective are:

  • a statement that the contract comprises the entire agreement between the parties, and that the contract supersedes any agreements that were made previously;
  • a statement that the parties have not relied on any representation not set out in the contract;
  • an acceptance that the only remedy available to the parties is breach of contract, or any other remedies set out in the contract.

Exclusive remedies clauses

An exclusive remedies clause ensures that a party's remedy for any breach of contract is restricted to the remedies set out in the contract, and excludes all common law and other remedies. Exclusive remedies greatly reduce the scope for claims in relation to the contract which means they can be very useful, particularly if you are likely to be the paying party.

Tort is one of the remedies which would be available to a wronged party outside of a contract if an exclusive remedies clause is not used. A claim for damages in tort may be available to a party who has been wronged but who cannot claim a remedy under contract law, whether this is because there is no contractual remedy available or because there was no contract in the first place.

The same requirements apply to exclusive remedies clauses as apply to any other type of exclusion clause, including the 'reasonableness' test under UCTA above.

It is important to check that any exclusive remedies provisions in the main contract are properly mirrored in any subcontract. If not, the contractor will bear the risk of any gaps.

Liquidated damages

Liquidated damages (LDs) are damages, fixed in advance, which are built into certain construction contracts. The effect of an LDs clause is that it prevents the wronged party from claiming general damages under a contract, effectively operating as an exclusive remedy. In this sense, an LD clause acts as an exclusive remedies clause.

For more information about LD clauses, please see our separate OUT-LAW Guide. Briefly, however, in order to be enforceable an LD clause must be a genuine pre-estimate of any loss likely to be sustained, rather than a penalty designed to deter a party from breaching the contract in the first place.

If an LD clause is regarded as being a penalty or is too vague to be enforced, general damages may still be available as a fallback.

Drafting issues

In order to avoid being caught out, here are some of the issues you should consider when drafting or negotiating an exclusion clause:

  • identify your commercial concerns – what sort of losses will be most significant to your business? Which losses will you want to recover?
  • identify what types of loss should be excluded. It is standard practice to limit to employer's losses, but there may be a reason to also limit the contractor's losses such as loss of profit if part of the works contracted for is subsequently not needed;
  • clear and unambiguous wording is essential. Widely drafted working, such as exclusion of 'indirect or consequential' losses, may not exclude loss of profit or revenue if the court considers this to be a 'direct' loss which was in contemplation of the parties when they entered into the contract. Whether a loss is 'direct' or 'consequential' can only be decided on a case-specific basis – see Out-Law guide to direct and indirect loss for contractors for more information;
  • decide whether any claim for loss should be subject to notice provisions, and whether a claim will be enforceable if proper notice is not given;
  • decide whether there should be a cap on any losses, and if so whether it should be for losses over a fixed period or over the whole duration of the contract. Consider whether the cap should be different for different types of loss;
  • bear in mind that certain liabilities cannot be excluded – usually liability for fraud, negligently caused death or personal injury. If these are excluded, any such clause may be void;
  • look at the effect of the exclusion clause in relation to any insurance arrangements. Uninsured and insured losses may require different treatment;
  • ensure that any limitation provisions are reflected in subcontract.
We are processing your request. \n Thank you for your patience. An error occurred. This could be due to inactivity on the page - please try again.