Many construction contracts make the giving of notice of claim a pre-condition to the entitlement to claim additional time or money; so that if notice is not given within a specified time limit from the event or circumstance giving rise to the claim then the right to claim is lost. This commonly gives rise to disputes as to entitlement; where the focus all too often is on whether the notice was procedurally compliant, as opposed to the parties engaging to resolve the substance of the claim, which may be perfectly good.
The giving of notices to suspend or terminate is required in order to be entitled to exercise that contractual right. If the specified notice period is not complied with, or the notice is not given in accordance with the form and prescribed method under the contract, the notice may be considered invalid. The issue of manner and form non-compliance can give rise to arguments that the subsequent exercise of the right to suspend or terminate was equally invalid. In common law jurisdictions, this might be taken to be a repudiatory breach entitling the other party to terminate - turning the tables and exposing the party that failed to give proper notice to significant damages.
Prescribed method for giving notice
Construction contracts will usually prescribe a common method for the giving of notices. It will normally require notices to be given in writing and prescribe the accepted methods of delivery - post, courier, fax, email etc. - as well as when the notice will be deemed to have occurred depending on the mode of delivery used.
When giving notice, it is important to be aware of and comply with these requirements to avoid arguments later that valid notice has not been given. For more information on the practicalities of giving notice and delivery, see our Out-Law guide to notice provisions in construction contracts.
Timing of your notice
Contractual provisions providing for additional time and payment will often require that notice be given within a set period from when the contractor became aware - or ought to have been aware - of the event or circumstance giving rise to the claim.
Notifying within that prescribed period is usually a condition precedent to the claim. This means that if the claim is notified later than the prescribed period, the right to claim may be lost.
It is therefore important to put appropriate project controls in place to identify events which may give rise to additional time or money during the project, to ensure that this triggers the giving of notice within the prescribed period. One way to do this is by including risk registers in weekly or monthly reporting functions, which are designed to pick up risk events early on so that notice can then be given in the prescribed form under the contract in time.
When seeking to suspend or terminate, construction contracts require the giving of 'notice to cure', which triggers a cure period, after which the right to suspend or terminate can be exercised. Since the cure period starts when delivery is deemed to have occurred, it is particularly important to know when notice is deemed to have been received to avoid exercising the right to suspend or terminate prematurely. This may result in the loss of the right to suspend or terminate. As mentioned above, it may also attract liability for repudiatory breach.
Contents and frequency of notices
It is important to check whether the contract calls for a particular form of notice. If it does, that form should be followed.
When dealing with claims for additional time or payment and the invoking of immunity from liability for non-performance - for example, under a force majeure clause - it is best for the notice to state that it is intended to notify a claim or seek immunity. The notice should also provide as much information as possible about the event giving rise to the claim. It would also be best to state the clauses under which the claim is being made.
If the contract does not contain prescriptive requirements as to the form and contents of the notice, some leeway will generally be given to the contractor given the harsh consequences of failing to notify the claim. In a 2014 case between a contractor and the attorney general for Gibraltar, the English High Court confirmed that the broad test under English law is that the notice must be recognisable as a claim.
Where the effects of an event, like Covid-19, might give rise to different entitlements or immunities under the contract, or even at law, it is important to ensure that the notice is drafted broadly to capture those different causes of action or doctrines of immunity in order to reduce arguments that the notice is not broad enough to cover the relief that may ultimately be sought.
Consideration should also be given to whether any subsequent notices are needed. For example, the impact of Covid-19 may have triggered a force majeure clause, but changes in law in response to the pandemic may themselves have triggered entitlement to relief - and, importantly, additional payment - under the change in law provisions. Since the change in law came later, the obligation to notify under the change in law provisions may also be said to come later.
Covid-19 may continue to impact in future, with possibility of future unplanned lockdowns giving rise to fresh delay and claims for further additional payment. In those circumstances, parties should give fresh notice to avoid arguments as to whether notice has properly been given.