The same principle works the other way too. If, under the main contract, the employer is obliged to do something within five days, the contractor may need time to reflect before passing any relevant information onto the subcontractor. In this example, the timescale in the subcontract should be longer – for example, 10 business days.
Time periods and buffers are also important in respect of payment obligations. The relevant NEC4 contract forms already incorporate time buffers into the payment provisions. For example, at clause 51.1, payments in the main contract are certified by the project manager within one week of the assessment date; and payments in the subcontract are certified by the contractor within two weeks of the assessment date. At clause Y2.2, the date on which a payment becomes due is seven days after the assessment date in the ECC and 14 days in the ECS.
In practical terms, there is therefore a seven day buffer both for certifying the payments and for making payment. There is scope to amend these periods so that there is a greater buffer – although care should be taken to ensure compliance with employer payment policies, for example the government’s prompt payment policy, which requires undisputed invoices to be paid within 30 days and for this payment term to be passed down the supply chain.
If the NEC forms of subcontract are not used, the draftsperson will need to ensure that adequate buffers are included and specifically drafted for.
Mandatory v discretionary flowdown
Depending on the terms of the main contract, the contractor may be obliged to include certain provisions in the subcontract. We often see this in relation to policy clauses, such as those around bribery and modern slavery – for example, a contractor may be required to comply with the employer’s bribery policy and include provisions in its subcontracts to ensure its subcontractors do the same. It is not usually found in respect of the core contract obligations, because the employer will usually give the contractor discretion about how to procure its supply chain.
Where flowing down obligations under the main contract to the subcontract is not mandatory, you may still choose to do so in order to rely on the subcontractor’s assistance with those obligations at a later date.