The High Court did, though, consider what compensation can be claimed for works carried out that are incomplete. The judges were split on the question of whether the remedy of quantum meruit can be claimed in such circumstances, but the majority decided that the contractor may elect to claim either contractual damages or an amount representing a fair value of the work performed for incomplete work, with the value of what is payable to be capped at the contract price for that part of the work.
Construction disputes expert Gemma Thomas of Pinsent Masons said: "Quantum meruit claims were revered among contractors because they provided an opportunity to recover all costs reasonably incurred on a project. This was a particularly attractive avenue for contractors engaged on loss-making contracts. However, the remedy of quantum meruit also attracted a lot of criticism with the greatest being that the law should not ignore an otherwise enforceable bargain struck by the parties."
Croagh and Thomas said the High Court's ruling does not close off the option of termination for contractors where they are locked into loss-making contracts, but they said the risks of terminating agreements must be carefully considered.
"The judgment adds another layer of complexity to the decision of whether to terminate or not in that the contractor will need to weigh up the risks of termination against the compensation they might be entitled to and the future losses they might be able to avoid," Croagh said. "Their likely compensation will need to be calculated by adding up the contractor's accrued rights to payment plus fair value of the works performed under any incomplete portions capped at the contract price, alternatively contractual damages."
"It is also worthwhile remembering that the contractors is not necessarily limited to its rights under the contract. There may be avenues available to a contractor to recover under the Australian Consumer Law, for example," he said.